- Remove the soft and water-damaged flooring and the old tile in both units, and gut both bathrooms — tubs, tile and fixtures.
- Whole-ceiling drywall removal in both units, plus the selective partition and closet wall demolition per the plan markups, including the wall cut-outs needed for the plumbing and electrical work.
- All debris hauled off — dumpster drop, pull and disposal fees included.
- Foundation repair on both units, top-down.
- Subfloor replacement, floor joist and beam replacement, and completion of the partial sistering.
- Replacement of the termite-damaged framing found under the structure.
| Service | Price |
|---|---|
| 10101 Demolition & Trashout Remove the soft and water-damaged flooring and the old tile in both units, and gut both bathrooms — tubs, tile and fixtures. · Whole-ceiling drywall removal in both units, plus the selective partition and closet wall demolition per the plan markups, including the wall cut-outs needed for the plumbing and electrical work. · All debris hauled off — dumpster drop, pull and disposal fees included. |
$9,500.00 |
| 10103 Structural Package Foundation repair on both units, top-down. · Subfloor replacement, floor joist and beam replacement, and completion of the partial sistering. · Replacement of the termite-damaged framing found under the structure. |
$26,500.00 |
| Total | $36,000.00 |
Scope: the accepted demolition and structural package for the two-unit duplex at 213 South Birdneck Rd — both units. No other trade is part of this invoice.
Notes: the jobsite is left clean once the work is complete. Unforeseen concealed conditions — hidden rot or termite damage beyond the inspected areas — are documented and presented for written approval before that work proceeds.
Warranty: one (1) year workmanship on the structural framing, floor leveling / subfloor and general trades from substantial completion.
Not included: the balance of the duplex renovation — roofing, windows and exterior doors, siding, framing, insulation, drywall, trim, painting, cabinets and countertops, tile, flooring, appliances, plumbing, electrical and HVAC. Those lines remain available on the full estimate.
Payment: Total Project Cost $36,000.00 — Deposit to Schedule $18,000.00, Final Payment $18,000.00.
Check is a preferred method.
Pay by credit card: request.plastiq.com/pay-tidewater-home-improvement-llc
Cards not eligible for payment: Virtual Affirm credit card